Project Update – Refurb Africa Project August 29
Ijedodo Mosque 1 - This week they are tiling Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue fixing the windows Ma'sha Allah.
Bayelsa Mosque...
Project Update – Refurb Africa Project August 22
Ijedodo Mosque 3 - This week they are fixing the window and door Ma'sha Allah.
Bayelsa Mosque - This week they continue fixing the ceiling...
Project Update – Refurb Africa Project August 15
Ijedodo Mosque 3 - This week they are preparing the window areas and frames Ma'sha Allah.
Bayelsa Mosque - This week they are fixing the...
Project Update – Refurb Africa Project August 9
Ijedodo Mosque 1 - This week they continue tiling Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue fixing the ceiling Ma'sha Allah
Please do...
Project Update – Refurb Africa Project August 2
Ijedodo Mosque 1 - This week they bought a truck of plaster sand and are tiling the Imam's area.
Ijedodo Mosque 3 - This week...