Project Update – Refurb Africa Project June 24
Ijedodo Central Mosque, Lagos - This week they are completing the casting of the first floor pillars, Alhamdulillah.
~
Please do support by donating and sharing....
Project Update – Refurb Africa Project June 17
Ijedodo Central Mosque, Lagos - This week the plastering of the ground floor walls continues and they have purchased the steel for the first floor...
Project Update – Refurb Africa Project June 10
Ijedodo Central Mosque, Lagos - This week the electrical work and plastering of the ground floor walls continues, Alhamdulillah...
~
Please do support by donating and sharing....
Project Update – Refurb Africa Project June 3
Ijedodo Central Mosque, Lagos - This week the electrical work and plastering of the ground floor walls continues, Alhamdulillah...
~
Please do support by donating and sharing....