Project Update – Refurb Africa Project November 28
Ijedodo Mosque 1 - This week they continue tiling the outside Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue plastering the walls and...
Project Update – Refurb Africa Project November 21
Ijedodo Mosque 1 - This week they continue tiling the outside Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue plastering the walls and...
Project Update – Refurb Africa Project November 14
Ijedodo Mosque 1 - This week they continue tiling the outside Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue plastering the walls and...
Project Update – Refurb Africa Project November 7
Ijedodo Mosque 1 - This week they continue tiling the outside Ma'sha Allah.
Bayelsa Mosque - This week they continue tiling the patio Ma'sha Allah
Please...
Project Update – Refurb Africa Project October 31
Ijedodo Mosque 1 - This week they continue tiling the outside Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue plastering the walls and...
Project Update – Refurb Africa Project October 24
Ijedodo Mosque 1 - This week they continue tiling Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue plastering the walls Ma'sha Allah.
Bayelsa Mosque...
Project Update – Refurb Africa Project October 17
Ijedodo Mosque 1 - This week they continue tiling Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue plastering the walls Ma'sha Allah.
Bayelsa Mosque...
Project Update – Refurb Africa Project October 10
Ijedodo Mosque 1 - This week they continue tiling Ma'sha Allah.
Ijedodo Mosque 3 - This week they are plastering the walls and pillars Ma'sha...
Project Update – Refurb Africa Project October 3
Ijedodo Mosque 1 - This week they continue tiling Ma'sha Allah.
Ijedodo Mosque 3 - This week they continue fixing the door and plastering the...
Project Update – Refurb Africa Project September 26
Ijedodo Mosque 3 - This week they continue plastering the walls and ceiling Ma'sha Allah.
Bayelsa Mosque - This week they continue fixing the ceiling Ma'sha...